Atlantic Yards/Pacific Park infographics: what's built/what's coming/what's missing, who's responsible, + project FAQ/timeline (pinned post)

From the latest Construction Update: completion of B2 modular tower may require second shift (til 11 pm?)

According to the latest Atlantic Yards/Pacific Park Construction Update, (bottom) covering the two weeks beginning yesterday and circulated yesterday at 1:14 pm (late) by Empire State Development after preparation by Greenland Forest City Partners, the push to finish the B2 modular tower (aka 461 Dean Street) may require a second shift.

The time wasn't specified, but I presume it's in the range of 3 to 11 pm. It's unclear how noisy the work would be, but it could include exterior facade adjustments. The tower is supposed to open by September or October

Saturday work is also expected at this site, at the corner of Flatbush Avenue and Dean Street, as well as other sites, including B3 (38 Sixth Avenue),  B11 (550 Vanderbilt Avenue), B12 (615 Dean Street), and B14 (535 Carlton Avenue).

Starting next week, as early as May 15, there will be "mobilizing and prep work for sewer relining within the project site in Pacific Street between Vanderbilt and 6th Avenues. Work involves video [?], cleaning and vacuuming operations. Including using a large size jet and vacuum truck and support vans on the existing sewer main below Pacific Street. Access to sewer main will be via the street manholes."